BLCP Power Station is designed to cause minimal pollution and continuously monitor and control emissions to levels within both international and government standards.

The Coal Unloading Facility

is adjacent to the BLCP Power Station (does not extend into deep sea) and uses semi-closed-to closed mechanical belt conveyor and water sprays to prevent the spread of dust.

 

The Coal Unloading Facility

 

 

The Coal Stockpile

BLCP Power Station uses a wind fence, compaction of dead stock with grass covered, water sprays and a row of trees for wind and dust protection.

 

The Coal Stockpile

 

 

 

BLCP Power Station

BLCP Power Station generates 1,434 Megawatts of power using about 3.64 million tons of good quality of bituminuos coal per year and installed with Flue Gas Desulfurization (FGD), Electrostatic Precipitator (ESP) , Low NOx Burner, waste water treatment system and environment management equipment at a cost of over 14,000 million baht or 25% of total investment.

 